WB delegation inspects Mukalla, Ba-Wazir drainage projects
The Source: /www.sabanews.net - 29/04/2009
Home \
Local News
A World Bank (WB) delegation headed by the follow-up expert of water and sanitation projects in the Middle East Alex Bakelian inspected on Wednesday the ongoing works of Mukalha and Ba-Wazir drainage projects. The delegation was briefed on the percentage of achievement in the two projects, ranged between 70%-97% at an amount of YR7.6 billion financed by the WB. The reasons for the delay of completion, according to the contracts agreed on and specified at the end of 2008, were also reviewed. The delegation emphasized the importance of expediting the completion of the projects according to the new specified date in September 2009
|