Three dams at $630,000 in Hodeidah to be implemented
[The Source: www.sabanews.net - 25/1/2009]
The Field Unit at Tehama Development Authority (TDA) started
construction works
in three dams in Siham and Jahif valleys in Hudeidah
governorate at a total cost of $630,000 in the current January. The
dams, which are financed by the Yemeni government and World Bank within
the framework of Groundwater and Soil Conservation Project (GSCP), are
a dam of 100m length with two feeding and filtering gates at a cost of
$350,000 in Sharifiah, the other one in Jahif at a cost of $150,000 and
the third Shalaeih's dam is at a cost of $130,000 in Jahif. These
dams will help in expanding the agricultural area in the two valleys,
exploiting the rainwater properly and protecting the neighboring
villages and different buildings from the heavy rains hazards .
|